building The Foundry

December 2021, metal panel installation around clearstory windows


CONSTRUCTION summary

The City of Cambridge managed the Foundry construction project. CambridgeSeven architects developed a design that resulted in a LEED Gold, all electric energy, efficient space with modern systems that also highlights the building’s historic beauty.

April 2022, Third floor office space

Demolition of the Foundry’s interior started in late fall 2019. The project saw delays in 2020 due to COVID. The full construction project was substantially completed and received a Certificate of Occupancy in August 2022, with all final “punch list” items completed by the spring of 2023.

April 2022, Wood Shop

March 2022, nearly complete installation of metal panels on Addition

August 2021, view from 3rd Floor

August 2021, view from 3rd Floor

July 2021, New windows on Rogers Street facade.

July 2021, New windows on Rogers Street facade.

May 2021, New roof wood decking, with openings for skylights, looking down community hall towards performance space.

May 2021, New roof wood decking, with openings for skylights, looking down community hall towards performance space.

March 2021, Finishing concrete on the third floor

March 2021, Finishing concrete on the third floor

Feb 2021 Structural steel in new addition

Feb 2021 Structural steel in new addition

July - September 2022

  • Interior finish work completed

  • Solar PV system connected to the power grid

  • Furniture and equipment installation

  • Final exterior landscaping completed

  • Building systems testing and commissioning

  • Entry doors and internal security installed

April - June 2022

  • Permanent power turned on

  • Complete ductwork installation on first floor

  • Complete interior finishes

  • Complete new sidewalks on Rogers Street

  • Continued repaving work on Rogers street

  • Complete installation of the main entry canopy

  • Start installation of planters and other items in exterior side yard

  • Submit final purchase orders for furniture, fixtures and equipment

  • Start commissioning building systems and prepare for hand off to the Foundry Consortium

  • Ribbon Cutting planning for June 22nd

January - March 2022

  • Continued drywall installation

  • Continued ductwork installation

  • Complete exterior metal panel installation

  • Installation of interior finishes, including carpeting, tile, and paint

  • Bathrooms installation

  • Rogers Street road and sidewalk replacement underway

  • Installation of main entry canopy

  • Purchase orders made for FFE (furniture, fixtures, equipment)

September - December 2022

  • Completion of raised intersection by Third and Rogers

  • Continued drywall installation

  • Continued fire protection and electrical work

  • Continud ductwork installation

  • Complete window installation

  • Exterior metal panel installation

  • Excavation of side yard to prepare for exterior courtyard

  • See participation of Minority and Women Owned Business Enterprises as of October 2021 on Foundry project

August 2022

  • Drywall installation

  • Ductwork installation

  • Continued window installation

  • Continued rough in of fire protection and electrical

  • Installation of roof on the addition

  • Installation of concrete base for raised intersection by Third & Rogers

July 2022

  • Installation of first floor concrete slab on grade

  • Metal framing of partition walls

  • Rough in of HVAC, fire protection and electrical

  • New roof installation

  • Window installation

June 2021

  • Installation of first floor vapor barrier

  • Interior partition and door framing

  • Installation of sheathing on addition exterior

May 2021

  • Installation of new wood roof decking

  • Installation of reinforcing steel on the addition roof

  • Installation of exterior wall framing on the addition

April 2021

  • Complete masonry restoration

  • High roof truss repairs

  • Asbestos abatement of part of the tongue and groove roof decking

  • Demolition of unsalvageable tongue and groove roof decking

  • Completion of structural steel for addition

  • First floor slab on grade installation in historic building

  • Placement of transformer vault conduits

  • HVAC rough in on third floor

March 2021

  • Masonry restoration/cleaning

  • Complete installation of structural steel into the historic structure

  • Continue structural steel installation in building addition (the new additions is replacing a 1980’s addition that was no longer sound)

  • Complete installation of third floor concrete slab on deck

February 2021

  • Install site drainage and electrical utilities

  • Continue Masonry demolition and reconstruction

  • Structural steel erection for building addition

  • Install 3rd Floor concrete slab on deck at existing building

  • Install underslab Plumbing and Electrical at existing building

Fall 2020

  • Complete Interior excavation

  • Install support of building/excavation

  • Install concrete foundation in existing building and new addition