building The Foundry
CONSTRUCTION summary
The City of Cambridge managed the Foundry construction project. CambridgeSeven architects developed a design that resulted in a LEED Gold, all electric energy, efficient space with modern systems that also highlights the building’s historic beauty.
Demolition of the Foundry’s interior started in late fall 2019. The project saw delays in 2020 due to COVID. The full construction project was substantially completed and received a Certificate of Occupancy in August 2022, with all final “punch list” items completed by the spring of 2023.
July - September 2022
Interior finish work completed
Solar PV system connected to the power grid
Furniture and equipment installation
Final exterior landscaping completed
Building systems testing and commissioning
Entry doors and internal security installed
April - June 2022
Permanent power turned on
Complete ductwork installation on first floor
Complete interior finishes
Complete new sidewalks on Rogers Street
Continued repaving work on Rogers street
Complete installation of the main entry canopy
Start installation of planters and other items in exterior side yard
Submit final purchase orders for furniture, fixtures and equipment
Start commissioning building systems and prepare for hand off to the Foundry Consortium
Ribbon Cutting planning for June 22nd
January - March 2022
Continued drywall installation
Continued ductwork installation
Complete exterior metal panel installation
Installation of interior finishes, including carpeting, tile, and paint
Bathrooms installation
Rogers Street road and sidewalk replacement underway
Installation of main entry canopy
Purchase orders made for FFE (furniture, fixtures, equipment)
September - December 2022
Completion of raised intersection by Third and Rogers
Continued drywall installation
Continued fire protection and electrical work
Continud ductwork installation
Complete window installation
Exterior metal panel installation
Excavation of side yard to prepare for exterior courtyard
See participation of Minority and Women Owned Business Enterprises as of October 2021 on Foundry project
August 2022
Drywall installation
Ductwork installation
Continued window installation
Continued rough in of fire protection and electrical
Installation of roof on the addition
Installation of concrete base for raised intersection by Third & Rogers
July 2022
Installation of first floor concrete slab on grade
Metal framing of partition walls
Rough in of HVAC, fire protection and electrical
New roof installation
Window installation
June 2021
Installation of first floor vapor barrier
Interior partition and door framing
Installation of sheathing on addition exterior
May 2021
Installation of new wood roof decking
Installation of reinforcing steel on the addition roof
Installation of exterior wall framing on the addition
April 2021
Complete masonry restoration
High roof truss repairs
Asbestos abatement of part of the tongue and groove roof decking
Demolition of unsalvageable tongue and groove roof decking
Completion of structural steel for addition
First floor slab on grade installation in historic building
Placement of transformer vault conduits
HVAC rough in on third floor
March 2021
Masonry restoration/cleaning
Complete installation of structural steel into the historic structure
Continue structural steel installation in building addition (the new additions is replacing a 1980’s addition that was no longer sound)
Complete installation of third floor concrete slab on deck
February 2021
Install site drainage and electrical utilities
Continue Masonry demolition and reconstruction
Structural steel erection for building addition
Install 3rd Floor concrete slab on deck at existing building
Install underslab Plumbing and Electrical at existing building
Fall 2020
Complete Interior excavation
Install support of building/excavation
Install concrete foundation in existing building and new addition